Represented Unatrac International (a UK IPP) in connection with the establishment of an off-grid power plant capable of generating 12,000 kilowatts of electricity for Cement Company of Northern Nigeria.
We drafted and negotiated the Power Purchase Agreement for the Cross-River State Government sponsored Tinapa Business Resort 15MW IPP project.
Advised the World Bank funded Legal Workstream Consultancy, arranged for the Bureau of Public Enterprises, in connection with the unbundling of National Electric Power Authority (NEPA) and the establishment of the Power Holding Company of Nigeria Plc. and the Nigerian Electricity Regulatory Commission (NERC). Our duties included setting up New Business Unit successors of NEPA (6 Gencos, 1 Transco and 11 Discos), drafting Market Rules, Vesting Orders and Transmission