Highlights of the 60-Day National Action Plan on Ease of Doing Business in Nigeria
Posted on Sun 26 Mar 2017
- Download Resource
On Obtaining Construction Permits
The following reforms are being implemented by the LASG to ease doing business in Lagos State, the nation’s commercial capital:
S/No |
Identified Challenges |
Reforms (Ongoing & Completed) |
Results |
1 |
Construction permits’ procedures currently require manual submission of a large set of documents. |
Operationalise e-planning platform for Lagos State. |
|
2 |
Lack of clarity on applicable rules, fees, and procedures, and in what situations same applied. Also, lack of clarity on qualifications of architects and engineers who are empowered to supervise construction activities. |
|
|
3 |
Criteria for waiver of requirement for soil tests and environmental tests were unclear, and this appeared to be the time-consuming portion of the process for getting permits. |
Working to limit soil tests and Environmental Impact Assessment (EIA) only to specialized cases. |
|
The overall impact which the above reforms is expected to have is to reduce the time required to procure construction permits from forty-two (42) days to twenty (20) days.